The main points of the use of ductile iron pipes
Mar 18, 2022
1. Trench excavation
The bottom width of the groove should be calculated as follows: B=D1+2(b1+b2)
In the formula: B—the excavation width at the bottom of the pipe trench (mm) D1—the outer edge width of the pipe structure (mm) b1—the working face width on one side of the pipe (mm) b2—the supporting width on one side of the pipe (mm)
2. Groove support
The design is based on factors such as trench soil quality, groundwater, slotted section, and load conditions.
3. A buttress shall be provided at the vertical or horizontal turn of the T-joint pipeline. The size of the buttress shall be determined by calculation according to factors such as pipe diameter, rotation angle and working pressure.
4. When transporting drinking water, the pipeline should not pass through the poison-contaminated area. If it must pass through, protective measures should be taken.
5. All ductile iron pipelines connected by sockets and sockets must be designed with buttresses through calculation, refer to the National Building Standard Design Atlas 10S505 "Flexible Interface Water Supply Pipeline Buttresses".
6. For the outer anti-corrosion coating of ductile iron pipes, galvanized and epoxy asphalt coatings or coatings with higher requirements should be selected according to the soil conditions of the pipe laying site.
7. After the pipeline is installed and the pressure test is qualified, it should be rinsed with low chloride ion water and disinfected with 0.03% potassium permanganate aqueous solution.